Critical Path
The shortest route through a series of interrelated tasks. Should a task on the critical path slip then the end date of the project would be jeopardized.
Critical Path
Most projects contain a large number of tasks. The critical path is the order of tasks that must be finished for the project to be considered complete. This path dictates the final finish date of your project plan.
The critical path is not primarily a list of vital tasks. It is a specific sequence of tasks, each task depending on the last.
As the project progresses, different sequences might be named as critical. Consider a project with two vital task sequences which we'll call selecting the new office site and Moving in to new offices. At the onset, the first task is projected to take 9 months and the second is projected to take 6 months. Since the first task will take longer and is deemed as being on the critical path.
After three months work, should the first task perform ahead of schedule with a new estimate of 5 additional months more while the second has been delayed by three moths the latter task would now be on the critical path?
What is a Critical Task
The definition of a critical task is any task that with a change of duration may positively or negatively affect the end date of the project if delayed
Tracking the Critical Path
The Gantt chart and network diagram two classic views in MS Project will display critical tasks and links in red automatically to make these tasks easier to observe and report.
Slack Time
Total slack is the amount of time that lies off the critical path. In other words changes to the duration of these tasks may or may not affect the critical path.
Slack is the amount of time a task can be delayed and still be on schedule. A 5 day task with a 10 day deadline has 5 days of slack. A task with no slack is automatically critical. Imagine two tasks due to finish at the same time. Packing computer equipment with one day of duration and packing files with four days duration. If they both started at the same time the pack equipment tasks would have three days of slack.
For training materials on this topic www.mousetraining.co.uk/ms-office-training-manuals.html
If activity is accelerated in the critical path, then it may no longer be the critical path, assuming some other activity now takes longer.
Not necessarily. Critical path analysis determines the longest path through a network of project activities, because the main purpose of understanding the critical path is to focus effort on activities that lie on this path, thus increasing the chances of finishing the project on time. If you solely only focus on the critical path activities, then chances are that the activities not on the critical path will soon be on the new critical path because you haven't taken sufficient time to focus on all the activities. Project control should focus on the project as a whole, however more emphasis can be placed on the critical path activities as well as any risky/uncertain activities that could (if not monitored closely) eventually become a critical path activity and push the end date out even further.
The critical path helps you in determining how to accelerate your project by compressing tasks. Putting more people on critical path tasks and finishing it earlier will shorten the duration of the project (this is called crashing).
Yes. Practically that is perfectly possible. A Critical Path is the longest path between the start and end points and it is possible that there are multiple critical paths. Critical Paths are extremely important while creating a project schedule
The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date
If activity is accelerated in the critical path, then it may no longer be the critical path, assuming some other activity now takes longer.
Operation Determined Path happened in 2002.
Critical Path - video game - happened in 1994.
Critical Path - video game - was created in 1994.
In Project Management the Critical Path is the series of tasks that must finish on time for the entire project to finish on schedule. Each task on the critical path is a time critical task. You can also think of it as:the longest path from start to finishor the path without any slack,the path corresponding to the shortest time in which the project can be completed.
The importance of the Critical path is that helps you in reducing risk, contingency planning, and project planning.
The critical path is the sequence of activities that takes all dependencies into account. Thus, it determines the duration of the project, and is necessarily the longest path.
Critical Path
Not necessarily. Critical path analysis determines the longest path through a network of project activities, because the main purpose of understanding the critical path is to focus effort on activities that lie on this path, thus increasing the chances of finishing the project on time. If you solely only focus on the critical path activities, then chances are that the activities not on the critical path will soon be on the new critical path because you haven't taken sufficient time to focus on all the activities. Project control should focus on the project as a whole, however more emphasis can be placed on the critical path activities as well as any risky/uncertain activities that could (if not monitored closely) eventually become a critical path activity and push the end date out even further.
As per the Project Management Terminology, the longest path in a project sequence of activities is called the Critical Path. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date. Since this path is going to determine the schedule/delivery date of the project, it is called the critical path.
The critical path helps you in determining how to accelerate your project by compressing tasks. Putting more people on critical path tasks and finishing it earlier will shorten the duration of the project (this is called crashing).
The Critical Path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date. Critical Path is one of the key outputs of the Project Schedule Creation activity