In order to start to estimate the time and material for a steel building erection , first you will need to estimate the man hours required to determine the man-hours per square foot of building.
Erectors often can do a box 2400' building in as little as 4 days or .04 (men/hrs.) per sq.ft.)
Based on national averages of an experienced 4 man crew, the average time to erect a small 40 x 50 x 14,
(2000') is 4-5 days. To estimate the man hours (men/hrs.) based on these averages:
· Calculate: 4 men at 8 hours per day = 32 man-hours per day. 32 (men/hrs.) per day x 5 days = 160 (men/hrs.) per week.
· Divide 2000 sq.ft. By 160 = .08 (men/hrs.) per square foot. (Average .05-.10 per square foot)
Once you have estimated the man-hours per square foot, you can estimate the labor cost by taking the total man hours times the hourly wage per person.
Next, you would take the total number of days that you would need equipment rental and calculate the equipment rental cost and transportation.
Now, add your appropriate overhead for your monthly business expense. (Average 10- 25%)
Don't forget to ad travel time, insurance cost or any of the other above mentioned or job specific items.
Example: 40 x 50 x 14
2000 x .08 = 160 total man-hours x $25.00 per hour average $4,000.00 Labor
160 total (men/hrs) divided by 32 (men/hrs) day = 5 days rental at $500/day $2,500.00 Rental
Travel time and expense at $100/day (100 miles) $500.00 Travel
Subtotal $7,000.00
Add profit at 20% $1,400.00
Total Erection cost ($4.20') $8,400.00
Example: 100 x 100 x 18
10,000 x .06 = 600 total man hours x $25.00 per hour average $15,000.00 Labor
600 total (men/hrs) divided by 32(men/hrs) day = 18.75 days rental at $500/day $9,500.00 Rental
Travel time and expense (within 1 hour of jobsite) No Charge
Sub-total $24,500.00
Add overhead at 20% $4,900.00
Total Erection Cost (2.94') $29,400.00
These examples are given only as guidelines to assist a Builder in a method of evaluating final cost as you complete the work. Learning how to estimate the hours will also give the Builder some guidelines in ball parking the time and equipment rental to calculate if the rates of a sub-contract erector are reasonable. There are many other methods for estimating erecting cost and nothing is a substitute for experience.
The building itself cost $24,718,000 to build (nearly half the expected cost because of the Great Depression). Including the property on which the building sits, the total cost for the Empire State Building was $40,948,900
The cost to build a house in Kansas is about 100 per square foot to 125 per square foot. The final cost depends on the builder and the building materials that you use.
What is the typical per square foot cost to build in New Hampshire (not including land)?
The average cost per square foot for building a house in Wisconsin is about $110. This means a 1000 square foot house would cost about $110,000 to build.
how much does it cost for a 30-40 commerical building 6 inches thick
Between 95 and 110 dollars per square foot.
The average cost to build a new home in Mississippi will depend on its size and materials used. However, based on square footage, the estimated average cost per square foot is $80 to $100 according to builders and developers.
The average construction cost per square foot in central Virginia is about $125. This means a 200 square foot building would cost about $25,000 to build.
The average construction cost per square foot for a building addition in Ocean City, Maryland is about $130. This means an addition of 100 square feet would cost about $13,000 to build.
fifty dollars
The construction cost per square foot in Asheville, North Carolina is about $88 per square foot. This means a 3000 square foot building would cost about $264,000 to build.
The average cost per square foot for building a house in Ohio can range from $90 to $140. This means a 500 square foot house could cost between $45,000 and $70,000 to build.