The Question is mistake. The Question is How much sand and aggregate required for the one cubic meter of M20 grade concrete? Answer :- 20mm aggregate = 0.90M3 Sand = 0.45M3 to 0.5M3 depond on the Bulk density of Sand Cement = 320kg
FOR 1cubic meter of concrete block ,firstly we must know the mix ratio but if e.g we have the ratio of 1:2:4 ,
1 is cement
2 is sand
4 is aggregate
than we need these quantities for 1 meter cube
0.22 cubic meter cement which is 6.28 cement bags
0.44 cubic meter sand
and 0.88 cubic meter aggregates
To make 1Cubic Metre of Concrete you use 1 Cubic Metre of Crushed Rock or other coarse aggregate. You then add 1/2 cubic Metre 'washed sand', and 1/4 cubic Metre Portland Cement. Mix thoroughly while still dry then add the water progressively to the desired sloppiness.this gives the strongest concrete. The fact is, that all the sand and all the cement you add, simply fills up the air spaces between the pieces of crushed rock. So for 3 cubic Metre of Concrete you need the same volume of crushed rock, then half as much washed sand and one quarter as much cement.. The RATIO is 4:2:1 always. Bricklayers sand is not suitable because it contains clay and sometimes a little soil as well. It is very common to use the Ratio 5:2:1 for a cheaper slightly weaker concrete, and sometimes the Ratio 5:2&1/2:1 but 4:2:1 is ideal and most common. Concrete should be kept wet for at least 3 days to ensure it cures to a good strength. In hot weather hose the surface several times aday to keep it wet to encourage good strength or cover it from the hot sun with wet hessian, or white, heat reflective, plastic.
0.25 cubic metre is required.
Type your answer here... not now
how many bricks in 1 cft
1 and half tons
It takes 2L of water to make 1 kg of concrete. That is approximately 4800L per cubic meter.
Gravel occupies about 70-80% of the volume of concrete.It makes concrete economicalStrength of the concrete is determined only by the gravel. i.e., the body of the concrete.Property of concrete determined by the type of aggregate used.Shrinkage is less when larger size aggregate is used.
Each 60 pounds bag of ready mix concrete will make .45 cubic foot of concrete. There are 27 cubic feet in a cubic yard. You will need 60 bags of 60 pound premixed concrete to make 1 cubic yard.
Concrete is what you make a sidewalk from. To make concrete, you mix Portland cement, sand, gravel (aggregate) and water. The cement holds the aggregate together.
An 80 pound bag of premix concrete will make .6 cubic feet of cured concrete. There are 27 cubic feet in a cubic meter, so it would take 45 80 pound bags to make one cubic meter.
1 and half tons
twelve
I cant accuratly help you with the cement content but you need about 1 ton of sand and 1 ton of stone for every cubic meter of concrete. The cement content would depend on what you are using the concrete for. At 15 newtons of strength you would ( and this is just an educated guess) need about 95kg of OPC cement, 85kg of GGBS slag, 1.5lt of WRA (water reducing agent) and about 70lt of water to gain a 50mm slump per cubic meter. If I were you I would get it ready mixed. 70 Cube is a LOT of cocrete. Ready mixed 15 Newton concrete is about £75 inc vat per meter delivered. Regards Colin, a Tarmac concrete batcher.
15 milligrams
500 pounds cement, 1500 pounds sand, 1600 pounds gravel. Mix with 32 gallons water
It takes 2L of water to make 1 kg of concrete. That is approximately 4800L per cubic meter.
The main industrial use for gravel is to pave roads and paths. Gravel is also used to help make concrete.
I'll make the assumption that 150 is meant to be metres. 150x6 is 900, x 2.5 is 2250
Concrete.
The main industrial use for gravel is to pave roads and paths. Gravel is also used to help make concrete.
I'm assuming by bricki you mean aggregate? There are several different mixes of concrete that yield different strengths. One of the more common mixes is a 3/2/1 mix this combines 3 parts aggregate (crushed stone), 2 parts sand and 1 part portland cement. with this mixture to make 1 cubic meter of concrete you will need almost 1/2 cubic meter of aggregate, 1/3 cubic meter sand and 1/6 cubic meter portland cement mixed with about 75 liters of water. Different mixes use varying amounts of stone though the sand and cement mixture stays between 1 1/2 : 1 to 2:1