answersLogoWhite

0


Best Answer

The beginnings of all related dependent tasks are also delayed.

User Avatar

bob

Lvl 5
3y ago
This answer is:
User Avatar
More answers
User Avatar

Wiki User

7y ago

If the primary task is delayed, the entire project schedule will be delayed

This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What are the consequences to the schedule if completion of a primary task is delayed?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Continue Learning about Management

What are the primary roles of the project schedule?

It shows the resources responsible for carrying out activites, it lists all project activities


Why would a project manager benefit from distinguishing between primary tasks and dependent tasks?

This would enable the manager to draft a dependency schedule -Apex


What is project time management?

The primary purpose of project time management is to develop and control the project schedule. Any project has a timeline by which it is expected to be completed and a well managed project is expected to complete by the set timelines. This is accomplished by performing the following components: 1. Define activities - Identify all the work activities that need to be scheduled to produce the project deliverables. 2. Sequence activities - Identify the dependencies among the activities that need to be scheduled so that they can be scheduled in the correct order. 3. Estimate activity resources - For each schedule activity, estimate the types of resources needed and the quantity for each type. 4. Estimate activity durations - Estimate the time needed to complete each schedule activity. 5. Develop schedule - Analyze the data created in the previous steps to develop the schedule. 6. Control schedule - Control changes to the project schedule.


How do you manage a project time?

The primary purpose of project time management is to develop and control the project schedule. Any project has a timeline by which it is expected to be completed and a well managed project is expected to complete by the set timelines. This is accomplished by performing the following components: 1. Define activities - Identify all the work activities that need to be scheduled to produce the project deliverables. 2. Sequence activities - Identify the dependencies among the activities that need to be scheduled so that they can be scheduled in the correct order. 3. Estimate activity resources - For each schedule activity, estimate the types of resources needed and the quantity for each type. 4. Estimate activity durations - Estimate the time needed to complete each schedule activity. 5. Develop schedule - Analyze the data created in the previous steps to develop the schedule. 6. Control schedule - Control changes to the project schedule.


Why is management a primary component in entrepreneurial activity?

what is management primary component in entrepreneurial

Related questions

CPT Code for Delayed Primary Closure?

primary closure knee


What is the only symptom of primary amenorrhea?

The only symptom of primary amenorrhea is delayed menstruation.


What reading material is available on delayed puberty and primary amenorrhea?

Meduri, G., P. Touraine, I. Beau, et al. "Delayed Puberty and Primary Amenorrhea Associated with a Novel Mutation of the Human Follicle-Stimulating Hormone Receptor.


What is the primary goal of discipline?

To teach responsibility, the importance of task completion and self-discipline by example.


What Is A Delayed Start Lease?

The primary reason for a delayed start lease is when you do not have budget dollars in the current year. The equipment gets installed and paid for in the current year and the lease payments begin in the following year when budget dollars are on hand.


Secondary appraisal?

one's evaluation of his or her ability to cope with the consequences of an interaction with the environment, which follows a primary appraisal.


What are the primary causes of sleep deprivation?

There are many primary causes of sleep deprivation. Some of the primary causes of sleep deprivation includes insomnia, sleeping in an unsafe area, and having an odd sleeping schedule.


What is tertiary intention in wound healing?

Tertiary intention is delayed primary closure of a surgical wound. The wound that is too heavily contaminated for primary closure is left open after removal of all non-viable tissue.


What is Harminized Tarrif Schedule US?

The Harmonized Tariff Schedule of the United States is the primary way for determining tariff aka customs duties and fees for goods imported into the United States.


What are the primary roles of the project schedule?

It shows the resources responsible for carrying out activites, it lists all project activities


Who is the primary and secondary education minister of Andhra Pradesh?

Since there is president's rule in andhrapradesh, there will be no canbinet of ministers working until completion of elections in 2014


What was one of the primary consequences of the Council of Trent in art and architecture?

The major consequence of the Council of Trent in art and architecture is known as Florid Baroque.