Construction Documents start in the bidding phase and the binding contract documents consist of #'s 2-7

1. Bidding Requirements
Invitation to bid
Instructions to bidders
Information for bidders
Bid forms and Attachments
Bid Security forms (Bid Bonds)

2. Contract forms
Agreement
Performance Bond
Payment Bond
Certificates (Licenses)

3. Contract Conditions
General Conditions (AIA 201-____)
Supplementary Conditions

4. Specifications of divisions 1-16

5. Drawings

6. Addenda

7. Contract Modifications