Best Answer

A request to change the scope of a project based on the technology required for a product.

The schedule baseline from a previous similar project that's used to determine how best to manage delays in manufacturing.

Company procedures regarding change control, reviewed to determine the level at which a change request should be set.

A request to change the project schedule because the manufacturing process for a new product is taking longer than expected.

A request that the widget cutting process is changed after quality control processes find a high number of widgets larger than specification.

A change control procedure for fast tracking an important change.

A cost baseline from a previous similar project that's used to assess potential changes to the current project.

A request to correct a scope overrun after a team member added functionality not required to a product, affecting time and schedule forecasts.

User Avatar

Wiki User

9y ago
This answer is:
User Avatar
More answers
User Avatar

Wiki User

9y ago

Feedback on the actual cost of a deliverable on the date it is completed.

A comprehensive list of planned costs for each activity.

A toll that helps to review a change request and its impacts on all components of a project.

This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What examples are inputs to perform integrated change control process?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

How are the monitor and control project work and perform integrated change control process linked?

Change requests generated as a result of monitoring and control activities become an input the Perform Integrated Change Control Process


How are the monitor and control project work and perform integrated change control processes linked?

Change requests generated as a result of monitoring and control activities become an input the Perform Integrated Change Control Process


What are some examples of integrated science process skills?

none jajaja


What key principles of the perform integrated change control process should you follow?

-Project baselines should be changed only when necessary -Approved changes must be coordinated -The impact of change requests must be documented


What key principles of perform integrated change control process should you follow?

-Project baselines should be changed only when necessary -Approved changes must be coordinated -The impact of change requests must be documented


What examples are are inputs to the Perform Integrated Change Control Process?

-A cost baseline from a previous similar project that's used to assess potential changes to the current project -A request to correct a scope overrun after a team member added functionality not required to a product, affecting time and schedule forecasts -A change control procedure for fast tracking and important change -A request that the widget cutting process is changed after quality control processes find a high number of widgets larger than specification


What are some term of Process control in total quality management constituents?

what are some examples of process control in total quality management constituents?


What are the examples of activities that you may perform in the monitoring and controlling process group?

ensuring double compiling tracking


How is the close project or phase process linked to the direct and manage project work and perform integrated change control processes?

1) It uses accepented deliverables from the Validate SCope processes as inputs. 2) The project management plan, created or updated through the other processes, in an input to the close project or phase process


Which are examples of inputs to the monitor and control project work process?

Containers Contractors Environmental


Where is integrated pest management a practical form of pest control?

Integrated Pest Management can be practiced in most pest management situations. It is a process of setting threshold limits on pest activity Then instituting a process utilizing mechanical, environmental, and least toxic to most toxic control measures based on size and scale as well as risk of pest infestation.


What are the inputs to the Perform Integrated change control process?

-A cost baseline from a previous similar project that's used to assess potential changes to the current project -A request to correct a scope overrun after a team member added functionality not required to a product, affecting time and schedule forecasts -A change control procedure for fast tracking and important change -A request that the widget cutting process is changed after quality control processes find a high number of widgets larger than specification