What is slack in ms project?

Updated: 9/14/2023
User Avatar

Wiki User

13y ago

Best Answer

Description The Free Slack field contains the amount of time that a task can be delayed without delaying any successor (successor: A task that cannot start or finish until another task starts or finishes.) tasks. If the task has no successors, free slack is the amount of time that a task can be delayed without delaying the entire project's finish date.

See related link for more information.

User Avatar

Wiki User

13y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What is slack in ms project?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Continue Learning about Management

What is slack time in project management?

what is slack in project management


What is project slack?

Slack or Float is the amount of time an activity can get delayed without delaying the overall end date of a project


Why is slack important to the project manager?

Slack is important when managing a project because it's is very rare that things don't change while working on a project. Budgets change, schedules change, available resources change and so do task priorities. Without slack time it'll be very challenging to be able to manage the project in a flexible way without causing tasks to be stuck or not have time to handle urgent things that were introduced (that weren't planned ahead of time).


What is the importance of slack time critical activies and critical path?

According to Malhortra/Krajewski/Ritzman, In their book "Operations Management", The maximum length of time that a task can be delayed without procrastinating the whole project is called activity slack. Activity on a critical path has Zero slack. Information on slack is useful because it summit activities that call for close attention. In this respect, activity slack is the amount of timetable slippage that can be accepted for an activity before the entire project will be delayed. Slack at an activity is lessened when the assessed time duration of an activity is surpassed or when the planned start time for an activity must be put off because of resource considerations (1). 1- Malhortra Krajewski Ritzman, "Operations Management" , 9th Edition, Prentice Hall, NJ


What a critical path in a project is and how it is determined?

The longest route through a series of interrelated tasks. Should a task on the critical path slip then the end date of the project would be jeopardized. Critical Path Most projects contain a large number of tasks. The critical path is the order of tasks that must be finished for the project to be considered complete. This path dictates the final finish date of your project plan. The critical path is not primarily a list of vital tasks. It is a specific sequence of tasks, each task depending on the last. As the project progresses, different sequences might be named as critical. Consider a project with two vital task sequences which we'll call selecting the new office site and Moving in to new offices. At the onset, the first task is projected to take 9 months and the second is projected to take 6 months. Since the first task will take longer and is deemed as being on the critical path. After three months work, should the first task perform ahead of schedule with a new estimate of 5 additional months more while the second has been delayed by three moths the latter task would now be on the critical path? What is a Critical Task The definition of a critical task is any task that with a change of duration may positively or negatively affect the end date of the project if delayed Tracking the Critical Path The Gantt chart and network diagram two classic views in MS Project will display critical tasks and links in red automatically to make these tasks easier to observe and report. Slack Time Total slack is the amount of time that lies off the critical path. In other words changes to the duration of these tasks may or may not affect the critical path. Slack is the amount of time a task can be delayed and still be on schedule. A 5 day task with a 10 day deadline has 5 days of slack. A task with no slack is automatically critical. Imagine two tasks due to finish at the same time. Packing computer equipment with one day of duration and packing files with four days duration. If they both started at the same time the pack equipment tasks would have three days of slack. http://www.mousetraining.co.uk/training-manuals/Project2007.pdf for a training manual and quick key card

Related questions

What is slack time in project management?

what is slack in project management


What is project slack?

Slack or Float is the amount of time an activity can get delayed without delaying the overall end date of a project


What is the difference between ms project and ms Excel?

These different applications are for different purposes you may need both.Project for planning and supporting project workExcel for calculating stuff.


Distingui sh between total slack and free slack?

Free slack: The free slack of an activity is the time this activity can be delayed without impact on the following activity. Total slack: The total slack of an activity is the time this activity can be delayed without impact on the finish date of the project.


What is the differences between critical path and slack time?

the critical path determines the duration of the project and hence the finish date of the project given the start date. Slack time is relative to the total float.


Can m and ms be a science project?

what


Anyone have idea about MS Project Time Tracking Software is about?

It's a time tracking software that MS Project users can use.


Why is slack important to project manager?

Slack is important when managing a project because it's is very rare that things don't change while working on a project. Budgets change, schedules change, available resources change and so do task priorities. Without slack time it'll be very challenging to be able to manage the project in a flexible way without causing tasks to be stuck or not have time to handle urgent things that were introduced (that weren't planned ahead of time).


Why is slack important to the project manager?

Slack is important when managing a project because it's is very rare that things don't change while working on a project. Budgets change, schedules change, available resources change and so do task priorities. Without slack time it'll be very challenging to be able to manage the project in a flexible way without causing tasks to be stuck or not have time to handle urgent things that were introduced (that weren't planned ahead of time).


Consequences of budgetary slack?

Budgetary slack is a strategy that actively works to prevent a budget from working as designed. The consequence can be a business or project that fails due to apparently faulty budgeting.


MS project 2007 tutorial?

You can find a free Project 2007 quick Keycard and training manual at http://www.mousetraining.co.uk/ms-office-training-manuals.html


Can I download ms project software for free online?

The full MS Project software is not currently available legally for free download on the internet. However, you can download a MS Project reader for free that allows you to view projects but you cannot make edits or start new projects.